- Larry Leissner
We’re nearing the conclusion of this series that started
with the basics
of scheduling. I want to tie up a
few loose ends, maybe clarify some inaccuracies and address some confusion I
may have introduced.
As I developed this series on scheduling, leading up to the
previous post on estimate
buffers, I hopefully offered convincing arguments for including appropriate
buffers. In this post, I want to compare
and contrast various types of buffers that are common.
I think the discussion I offered on risk
buffers is consistent with other authors and industry practices, so I won’t
belabor that discussion. I will point
out that risk buffers are included in the project (time and cost) budget and
are managed by the Project Manager.
Literature and practices for improving
estimate confidence are much rarer.
Therefore, there may be some stakeholder pushback for including these
buffers in the schedule. However, you
can demonstrate through logic, reason, science and ethics that, in order to
have a realistic schedule, these buffers, like the risk buffers, must be
included in the schedule. Like risk
buffers, these confidence buffers are included in the project budget and are
managed by the Project Manager.
However, you don’t want to “double count” your risks. Let’s say you do a lot of similar projects. For these, there will probably be a common
pool of risks that are included.
However, if your estimates are based on historical results and sometimes
these risks occur, then there is the potential that your Pessimistic estimates
will already account for those risks. You
will need to adjust either the estimates or the risk buffers so they are in the
schedule only once.
In contrast to the confidence and risk buffers, some PMs Pad
their estimates. Some project managers,
after over-running the project schedule a few times, learn that their estimates
are never sufficient and start adding arbitrary amounts. “We go over by 20% every time, so I’ll just
start adding 20% to the schedule.” This
may sound logical on the surface, but is actually bad for their credibility and
for the PM profession. (Look for more
discussion on this topic in a future discussion of The Toyota Way.) Stakeholders learn that the PM is padding
and, in response, start cutting the budget or otherwise compensating. Pad is Bad.
In contrast, neither confidence
buffers nor risk
buffers are arbitrary. Hopefully, if
you’ve followed the discussion this far, the reasonable, logical and scientific
justification for including these in the project are thoroughly explained and
documented.
One last buffer that is sometimes seen in large, third-party
project contracts is Management Reserve.
Management Reserve is separate from and distinctly different than
estimate confidence buffers, risk buffers or pad. Management Reserve is contingency funds
allocated for use by the contract owner (sponsor). These funds are not part of the project
budget and are not available to the Project Manager except after approved
project change control to authorize allocation to the project.
I hope this series has been interesting and informative for
you. One last remaining post and then we
can move on to new topics.
Was this discussion scheduling and estimating clear and
thorough? Is there anything I missed
that you would like me to address or anything that is still not clear that I
should expand on?
© 2013 Chuck
Morton. All Rights Reserved.