"Thinking is more
interesting than knowing, but less interesting than looking.”
-
Johann Wolfgang von Goethe
This is the second post in the series on The
Project Status Report. In this post,
I get specific about the appropriate content of a PSR. But first, while it is called a Project Status
Report, it typically includes status (snapshot), trending, progress
(accomplishments) and exception (variance) content. Second, the PSR should not be confused with a
person’s (individual) status report (ISR), which everyone on the team should be
completing. Further, the PSR is not a roll-up
from the ISRs. Finally, the PSR, when
done properly, is aligned with and contributes to the overall Management by
Objectives (MBO) approach.
This last point deserves emphasis. The PSR does not and should not say what is
going on. I know this seems totally off
base, but to ignore this point devalues the PM contribution. Rather, the project has a plan and the PSR
documents the consistency with or variance from the plan. So rather than saying “what is going on,” the
PSR should say what is going on relative
to the plan, which is a key distinction.I’ve found that the following sections are useful to have in the PSR:
· Current snapshot
· Dashboard
· Performance to plan
· Accomplishments
· Planned for next period
· Issues/ Variances
· Acceptances
· Change activity
· Risk summary
· Downtime
Not all organizations use all sections and not all sections
are appropriate for all organizations.
Let me discuss each section.
Current snapshot
This optional section is status content and is the executive
summary of the PSR. It should be a very
brief (no more than a few sentences) narrative.
Of particular significance is to use this section to emphasize areas
where stakeholder intervention is required, such as resolving third-party
bureaucratic or administrative interference, stakeholder non-compliance
(failure to approve a deliverable or change request), failure of a risk or
issue owner to act, or when intervention is needed to address a “red light.”
Dashboard
This optional section is status content (and is improved
with trending indicators). Despite their
popularity, I’m not a big fan of “traffic lights,” those red-yellow-green
circles to summarize status, primarily because there often is not a clear
understanding by all stakeholders what the traffic lights mean. Further, a single traffic light summarizes
too much to be sufficiently actionable (for example, something I experience
regularly is that we will start a project before all of the budget
administrivia is complete, knowing that the executives have approved the
project and it will go forward. However,
the project shows red because of the budget and, so, everyone ignores the
traffic light. But there may also be
other factors that should be recognized that are concealed because of the
attention to the budget.)
I’m OK with traffic lights when the following conditions are
met: 1) all stakeholders understand what
the lights mean (in particular, when their action or intervention is
required); 2) that there are multiple
lights providing sufficiently discrete information to the stakeholders (e. g.,
budget, schedule, scope, approvals, issues, risks). Traffic light value is improved if there are
trending indicators (for example, up/ down arrows) to communicate changes.
Performance to plan
This is required status content. This should include a Gantt chart (showing
variance from plan) or, even better, Earned Value (and Earned Schedule)
graphs. This is the meat of the status
report.
Accomplishments
This is optional progress content, though it is universally
included. Equally universal is that the
wrong information is presented. This
should report accomplishments, not activity.
Avoid muddy verbs, such as:
worked on, met, attended.
Instead, use only concrete verbs, such as completed, published,
documented, tested, coded. The
activities associated with these verbs should be tasks or activities in the WBS
(and thus on the project schedule).
Finally, include metrics whenever possible (e.g., completed 20 of 30
test cases).
To digress momentarily, be clear about what “completed”
means. I often have developers report
they completed an assignment. “Have you
completed the unit testing,” I ask. “No,
I completed the coding.” OK, but the
task is not complete. These types of
grey areas compromise the accuracy and the credibility of your reporting.
Planned for next
period
This is optional progress content. The same rules as listed for Accomplishments
apply.
Issues/ Variances
This is required exception content and is usually a table
documenting current project issues, the issue owner, activity and plan for
resolution.
Acceptances
This is required status and exception content. This should be a table listing each
deliverable that has been submitted but not approved and deliverables that will
be submitted in the next few weeks.
Table columns should list the deliverable name, responsible approver,
date (to be) submitted, date approval was (or will be) due, and status (Not
submitted, Pending approval, Overdue, Approved). Overdue approvals should be highlighted. Once an approval is received, this is
reported as complete on the next PSR, then it is removed from future PSRs.
Change activity
This is required exception content. This, too, is a table listing each submitted,
but not completed, project
change request. Columns should
include PCR number, title, date submitted, date response due, and status
(Submitted, Pending approval, Approved/ Denied, Project plan updated). Once the PCR has been denied or after the
project plan is updated following the approval, this is reported on the next
PCR, then it is removed from the table.
Risk summary (key
risks)
This is required exception content. This section is formatted similar to the
Issues section. One thing important to
add to the section heading is “Date last discussed.” This should be the date that risks were most
recently discussed in the Client
Project Meeting with the stakeholders.
I find that these meetings rarely discuss risks because time runs out
before we get to this agenda item. Risks
should be discussed at least monthly and, if they haven’t been, this discussion
should be moved to the top part of the agenda.
Downtime
This is optional exception content and will rarely be seen
except in the status reports of the top echelon consulting firms. It really isn’t meaningful in a Product
& Service Delivery environment, but may mean the difference between
profit and loss for a Consultancy
PM. When the client is responsible
for the infrastructure on which the project depends, any failure, downtime, or force majeure where they are billed for
your services but no work is being performed because of their nonperfomance, should
be reported in this section. It should
(hopefully) be rare to have content here, but it is important to report it when
appropriate. I have also seen this
section used to report “thumb twiddling” time because a client has not given
timely approval to a deliverable.
There are obvious direct benefits from issuing weekly
project status reports. In the next and
final post on this series, some key indirect benefits that may not be obvious.
What benefits do you receive or would you expect from
publishing a weekly status report with this content? What project problems can be avoided? Can you guess what points I’ll bring up?
© 2013 Chuck
Morton. All Rights Reserved.
No comments:
Post a Comment