Showing posts with label Methodology. Show all posts
Showing posts with label Methodology. Show all posts

Thursday, August 14, 2014

Reconstructing Project Management (8 of 9)

Is Agile a project management discipline or really just a form of task or workstream management?

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.  © 2013 by the Project Management Institute
This is the penultimate entry in my series of posts commenting on nine questions that Peter Morris asked in his October article in Project Management Journal.

Agile is a mindset, not a methodology (or a process).  PMBoK defines a Body of Knowledge for creating a methodology (and processes), but it is not a methodology.  Agile is a way or practice or technique for delivering products or solutions.  So are SEI’s Capability Maturity Model – Integrated (CMMI) and the Microsoft Solution Framework (MSF).  Neither Agile, nor CMMI nor MSF are disciplines for delivering projects.  (For more on the relevance of this, I refer you back to an early series on the P&SD PM, the Consultancy PM,  and the philosophical relevance.)


Agilists are special only because they are so sensitive to anything that hints of management or structure.  Working with agile teams is similar to working with many creative types:  artists, painters, novelists, musicians and designers, for example.

What do we learn from this?  That there is so much market demand for a product delivery solution with PMI’s imprimatur that PMI has responded by offering the PMI-ACP®.  Should PMI also offer specialized domain-specific certifications for pharma research, product design, architecture, prototyping, etc?  Likewise, should they offer project management certifications for CMMI and MSF shops?
So I wandered off the trail and fell off a cliff.  Let’s get back on the main trail and respond to Morris’ question:  What Agile is is really not relevant.  That it’s not a discipline for delivering projects is all that matters.  And PMI is losing focus by responding to these distractions.

I get to drill deeper into that last comment in my next post.
© 2014 Chuck Morton.  All Rights Reserved.

Saturday, July 5, 2014

Reconstructing Project Management (7 of 9)

Is program management just the management of projects with shared aims and possibly resources or does it have some special ownership of delivery of the business case benefits?  If the latter, why?  Shouldn’t projects also have this concern?

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.  © 2013 by the Project Management Institute
This is the seventh in my series of posts
commenting on nine questions that Peter Morris asked in his October article in Project Management Journal. We are nearing completion of this series, with just a little wrap-up remaining.


In my previous post, I described a vision (or maybe it’s just a prediction) where senior leadership of the enterprise recognizes the value of enterprise (organizational) change management and the Project Management Office (PMO) is a strategically positioned general business service, on the order of Finance and HR.
In today’s world with generally weak PMOs, project management is in place to serve as agents of other organizational leaders – leaders who have strategic responsibility and delegate the tactical delivery to the PM agents.  As PM continues to mature and organizations recognize the value of organizational change, PMO oversight and management of the organizational portfolio will elevate PMO leadership first to valuation of the profit-loss (revenue vs cost) of the change portfolio and eventually to recognition of the asset value of the project portfolio.  This should happen naturally and organically, much as Finance moved from obscure back-office accounting responsibilities a century ago.

The real question is whether the leading project management organizations of today (such as PMI), recognize this evolution and take proactive measures to guide the future, or do they keep their feet securely grounded in the traditions of the profession and slowly wither into obscurity, or do they flounder reactively, without vision or philosophy, responding to the latest fad (to foreshadow the next post), until organizations realize that the value and esteem of the credential are so diminished that it is no longer relevant.
Here’s where I break with Morris:  What’s the point of this question?  What is a task?  What is a project?  What is a program?  Yes, PMI has its definitions, but are they adequate?  A project is composed of Deliverables, Activities and Tasks.  A well-defined task has a single owner.  It is a black box delegated to one person.   But, let’s say an executive tells his assistant “I’m going to the convention.  Get me a flight, hotel and car.”  Is that a project or a task?  It meets all of the components of the definition of a PMI project.

My point is that there is really nothing to distinguish a task from a project, except hierarchy.  Further, if you conceptualize a well-defined program as consisting of projects and deliverables (within those projects), then there is nothing really to distinguish a project from a program except hierarchy.  We have a natural recursive-descent system that just happens to have different names for nodes based on arbitrary values of size and scale (if you think that’s not true, compare your programs, projects, deliverables and tasks to NASA’s).
I realize Morris is trying to make a point about how PMI defines and explains these terms.  But he’s fixated on arbitrary labels.  To assume they’re inappropriate and then try to make sense of them just confuses me.  If they’re wrong, just say they’re wrong and offer up the improved definitions, conceptual framework and explanations.

So project management, whether that’s managing programs, projects, tasks, activities, deliverables or recipes (just tossed that one in to see if you’re paying attention), as I’ve explained over the past several posts, has to have a tactical delivery component and, at some level and possibly formalized at some point in the future, the strategic organizational-benefit elements.  It isn’t either-or.  Though it may be temporally not now, but then.
© 2014 Chuck Morton.  All Rights Reserved.

Thursday, June 26, 2014

Reconstructing Project Management (6 of 9)

Should project managers work to achieve effectiveness goals (value, functionality, business performance) or just stay with efficiency ones (on time, in budget, to scope, etc.)?

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.  © 2013 by the Project Management Institute
This is the sixth in my series of posts commenting on nine questions that Peter Morris asked in his October article in Project Management Journal.  With this question, we transition to a new, much more comfortable, area of inquiry.

Is it possible to distinguish between what a project manager does and what project management is?
 
In these posts responding to Morris’ questions, I have generally taken a practical, realistic, down-to-earth perspective.  In one way that makes sense:  I’m a practicing PM who works in the enterprise;  Morris is an academician.  I am pointing out the practical, realistic flaws with what I see as his ideal vision.  But that approach appears to put me in opposition to Morris.

And that is what is neither fair nor appropriate.  I support his vision.  It’s my vision, too.  My comments are not for the purpose of shooting down and deriding Morris’ vision, but rather that in exposing the cracks, we can seal them and strengthen the foundation of a broader, more strategic profession of project management.
Mike Rother, in Toyota Kata (2010) describes the Toyota continuous improvement practice of establishing a target condition and then working to achieve it (chapter 5).  The target condition has to be some better state and the approach for achieving it has to be unclear, to be determined.  The target condition is some future ideal state that the worker then, in incremental, experimental steps, strives, with their supervisor, to achieve.

I hear in Morris’ questions:  Are these the ideal states that the profession should be striving for (working toward) as the future of project management?  If so, and I believe so, then what is the next incremental step to get us there?
I actually see us already progressing in the right direction, though fitfully and reactively, rather than strategically, proactively and guided by a philosophical/ academic vision.  In the world of our past, companies were uncomfortable with change (projects), so they temporarily brought in specialists (PMs) to manage and drive the change.  As companies become more comfortable with change, as they recognize that change is continuous and that it’s necessary for competitive advantage and survival, they are institutionalizing the organizational change capability into a permanent, operational component of the organization.  It is called the Project Management Office (PMO).

With this evolution, the project manager role is changing.  Historically, the PM’s value was as a hired gun brought in to deliver a higher-level vision – that is, deliver the tactical expertise for planning, managing and controlling time, cost and scope – for benefit of a change agent within the organization.  This was how they were valued, rewarded, measured and compensated.
The PM of the future, though, will be a resource within the PMO.  The PMO will be responsible for delivering the change and will have developed criteria and methodologies for doing so.  The PM of the future will be rewarded, measured and compensated for compliance to and practice of the processes, use of the standard tools, and appropriate knowledge, skills and capabilities of the tools and processes.

So the flaw in Morris’ question, above, is that it should be “Should project management work to…”  Project managers of the future will still do the same tactical activities they do now – maintain schedules, track costs, calculate earned value, identify and manage risks, etc.  But they will do them following the proscribed processes of the PMO, rather than as craftsmen imbued with a mysterious skill.  It is the PMO that will do the meta-activities of managing a project:  Plan cost management, plan schedule management, plan risk management, plan procurement management, etc.
It is the PMO that will have the seat at the table to drive the enterprise effectiveness goals of the project, the program and the portfolio.

Regrettably, the poor PM of the future will not even have the golden triangle of constraints to point to when describing what they do.  They will have to pull out a thick procedures manual instead.
The future is sunnier for the profession, but the professional suffers.

© 2014 Chuck Morton.  All Rights Reserved.

Tuesday, June 24, 2014

Reconstructing Project Management (5 of 9)

Does project management cover Estimating and Contracts and Procurement?  Are they parts of the discipline? (Organizationally, they are often not treated this way.)

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.  © 2013 by the Project Management Institute
This is the fifth in my series of posts commenting on nine questions that Peter Morris asked in his October article in Project Management Journal.  Maybe I’ll finish this before the anniversary of its publication.




This is one of Morris’ questions that is a challenge to grasp because it seems the question is broken.  After all, Estimating is clearly defined in PMBoK planning processes for both cost and time management.  And Project Procurement Management is one of the 10 Knowledge Areas.  Therefore project management (at least, the PMBoK) does cover both of these topics and they are inarguably part of the discipline. What is Morris thinking?

Let’s think for a moment about how a government agency awards a contract for road or bridge building.  The agency will decide the road or bridge goes here, gets a budget allocated (estimation), buys up the necessary land (procurement) and only then issues the RFP for the engineering, design or construction firm to put steel and tarmac where the agency already decided it should go.
Lest you think that technology (my domain) is different, for large projects it is normal for executives to already have a cost limit, expected delivery date, expectation of technology partner, and whether the project will be done with in-house, outsourced or consulting resources – all before they let the project start through the official project methodology, phases and gates.

Morris expands further on this:  “similarly the project management team should provide input into commercial matters, beginning with the project strategy and the choice of contracting strategy;  in particular, what functions to contract out, what resources are available, and how risk should be allocated.  These typically come under the purview of the ‘Contracts and Procurement’ function but since they can all massively influence the way the project is managed, one would expect the project director (or equivalent) to be engaged, shaping thinking and decisions.  The alignment of supplier aims and practices with the sponsors’ aims should be a major objective in this new environment.”  (p18)
Are those activities project management?  Arguably, they are general (operational) business strategy and planning activities when they are done as part of business continuity, operations, development and growth.  But they are project management activities when done within the milieu of the project.  Should general business activities be project management when, ex post facto, they were done for what subsequently becomes a project?

I think it’s relevant to note a similarity that, in context, becomes, I guess, an analogy.  In technology, teams are generally matrixed and split responsibilities between projects and operations.  The operations responsibilities generally include support and maintenance.  Maintenance is planned and can be coordinated with project activities.  But support is on-demand and, on occasion, team members have to respond immediately to priority one situations that can take significant time away from the project.  And regardless of the project state, the support activity always takes precedence.  Ops trumps projects.  It’s just the way it is.  The point being, when the question arises, above, of whether these activities are operations or project, maybe ops trumps projects applies there, too.
© 2014 Chuck Morton.  All Rights Reserved.

Thursday, June 19, 2014

Reconstructing Project Management (4 of 9)

Should there be, resources allowing (personnel, funds), one [senior] person responsible for, and in charge of, the project from beginning-to-end?  (What does ‘beginning-to-end’ really mean?)

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.  © 2013 by the Project Management Institute
Well, yes, of course.  And with that I could be done with this post.

This is the fourth in my series of posts commenting on nine questions that Peter Morris asked in his October article in Project Management Journal.

 

The underlying intent of this question is, of course, much more complex and involved than a literal reading of the question indicates.

Morris, if I can presume to speak for him here, is implying that what we call project managers are only responsible for the tactical delivery of the project execution (monitor and control), but should be responsible for the strategic up-front initiation.  What I don’t know is if he believes that the Executive Vice-President of Finance, who currently has those up-front responsibilities, should be labeled the project manager or just that the PM should be seated at the table when the EVP is thinking about initiating this project.  I think realistic practice is that neither of those will (generally) happen any more than a department manager, who should be at the table when the executives are determining strategy for that department, will be there.  (Though it may evolve that the Chief Project Officer (CPO) of the enterprise of the future is at the table.)

In a top-down, command-and-control organization, someone at the top decides something needs to be done, when they need it done by, how much they’re willing to spend to get it done, and, in many cases, various levels of detail about how it will be done.  That executive who was there when the decision was made to start the project is  responsible and considers the project benefit to them, so they don’t want someone else getting the credit for the project’s success.  At the same time, that executive delegates, as they should, the tactical, day-to-day, delivery responsibilities of the project to someone who is qualified for that role and purpose.  I’m sure it’s only coincidental that the executive now has a scapegoat if the project goes south (we had a great plan that showed it was a major benefit;  it was only the delivery that failed).
So, executives should be held responsible just like bankers should’ve been responsible (i.e., paid the price) for the real estate collapse and financial meltdown, presidents should be held responsible for failed police actions and nation building across the globe, and officers shouldn’t get huge bonuses when their companies perform in the toilet.

I’m not being cynical (though I’m expressing cynicism with a broad, thick, dripping brush).  In fact, that is the reality of political maneuvering and a demonstration of the skills that successful people have and are able to apply.  If we called that top person a project manager and made them responsible, they’d still hire someone else for the delivery, delegate that responsibility to them and then take credit for the successful project while assigning responsibility for failure on the delivery technician, by whatever title.  Label the boxes what you will, it doesn’t change the results.
The bottom line is that I’m responsible for monitoring and controlling a project (which implies relative to a plan).  Delivering a result, a solution, a product or a service is not project management, whether it’s for an on-going operation or a temporary endeavor.  Those things can be done without project management (e.g., CMMI).

Something is a project if and only if there’s a plan for delivering it and there is monitoring and controlling relative to that plan.  The project manager is the person doing that monitoring and controlling, generally as a delegee on someone else’s behalf.
That’s what I do.

© 2014 Chuck Morton.  All Rights Reserved.

Saturday, June 14, 2014

Reconstructing Project Management (3 of 9)

When and how can we get away from a PMBOK that is based around what was chosen as being ‘the knowledge that is unique to project management’ rather than that which we need to know in order to develop and deliver projects successfully?

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.  © 2013 by the Project Management Institute

This is the third in my series of posts commenting on nine questions that Peter Morris asked in his October article in Project Management Journal.  This post takes up the third question, above, which needs a bit of context.




In the earliest editions of what is now PMBoK, PMI’s focus was only on the knowledge unique to project management, thus excluding general and domain-specific knowledge (though even this has questionable elements).  So, to know what you needed to know to manage projects, you had to know the PMBoK content as well as other stuff.
Morris has a fixation on PMBoK, even though he identifies several other BOKs (APM, IPMA, ENAA and EPMF) that don’t have this omission or limitation he identifies.  What I find most frustrating, though, when reading Morris is trying to determine what he means by the distinction of knowledge unique to PM vs what “we need to know in order to develop and deliver projects successfully.”  This is a refrain from both the PMJ article and the book, but I struggle to find concrete examples of content that should be present but isn’t.

It’s frustrating because I want to agree with Morris that PMBoK is incomplete, but I don’t just want to know the disease, I want the prescription to treat it, too. 
I think Morris is on much firmer grounding with his ninth question (to get ahead of myself) that challenges the foundation of PMBoK:  is it a reactive response to what PMs do or is it grounded solidly and strategically on a valid logical/ philosophical model that defines and encompasses the PM domain.  My interpretation is that PMI has been struggling over the past several years because their foundation is the Project Manager, but the future focus is on the PMO.  That is, historically the PM was responsible for delivering the project and was therefore responsible for cost, schedule and scope.

In the future, the team and the sponsor will have responsibility.  The PM will be responsible for (and measured by) following the processes and applying the tools that the PMO defines as appropriate within that organization for delivering successful projects.
PMI, thus, has lost its footing and is stumbling as it struggles to make this transition from the importance of the PM to the importance of PM processes.  OPM3 has the potential to lead the way, but it goes back to Morris’ ninth question:  is the PMBoK descriptive of what we do (and there are a lot of us doing a lot of different things called project management) or is it prescriptive and defining what is the domain and the boundaries of project management?  The latter is strategic and provides the leadership and vision for the future.  The former is historical and will be useful in a few years to analyze the demise of PMI.

© 2014 Chuck Morton.  All Rights Reserved.

Thursday, May 15, 2014

Reconstructing Project Management (2 of 9)


If it does not cover the front-end (a) is it fit-for-purpose (b) do we need an enlarged discipline or body of knowledge to cover what we need to know about managing the overall project?  (Since managing the front-end is key (i) in building-in value (ii)in building-in [or out] future problems.)

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.

In my previous post, I noted that I have started a series of posts commenting on nine questions that Peter Morris asked in his October article in Project Management Journal.  This post takes up the second question, above, which is a continuation of the previous post:  what is the “scope” of project management?

Some executives are tossing around ideas for boosting revenue.  They float this idea.  They float that idea.  At some point, somebody says, “That sounds good.  Let’s do a quick reality check to see if we should commit budget for it.”  If it doesn’t pan out – if it’s dropped without going through planning, execution and commission – was it ever a project?  If not, then when does something become a project?  When does this activity transition from on-going operational strategic leadership to a temporary endeavor?

If it does become a project, the vision, exploration and creation were surely part of the project, as was conceptualization, strategy, and the operational activities of enterprise leadership that normally precede “Let’s get a PM assigned.”  But are these exploratory and creative activities part of what we would call the project before the fact?  If they are, should a project management professional be engaged at these early stages?

How many project ideas have you known to originate from speculation about spending:  “If we do this project, we’ll be so much better off because our expenses will be $xxx.”  No, the project driver for discretionary projects is revenue and the factor that chills the enthusiasm is spending.  So it is that Morris talks about the front-end activities – the pre-project activities – that are not considered project management and are the responsibility of executive leadership, whereas the PM is responsible for controlling spending.

Yet, how can you separate the Yang of expenses from the Yin of revenue?  It wouldn’t be a project if it weren’t for the expected benefits.  But Brent Flyvbjerg lists a host of reasons why technological (longest, tallest, fastest), political (monuments and attention), economic (making money off the project) and aesthetic (design and iconism) sublimes can lead project originators to exaggerate the benefits and underestimate costs and difficulties (“What you should know about Megaprojects and Why: An overview,” Project Management Journal, April/May 2014, vol 45 #2, 6-19).

Further, as Peter Taylor explained in the December 17, 2013 webinar (PMI and INPDCoP membership required) “The Journey of Expectation Management” for the PMI Innovation and New Product Development Community of Practice, expectations (and constraints) for projects are often set and locked in before the project manager is engaged.  Yet, as Taylor goes on to say, it is the PM who is held responsible for project failure (often true even when the product is a resounding success:  the PM for the Ford Taurus project was reprimanded for going over budget;  the architect of the iconic, and 1,400% cost overrun, Sydney Opera House was so publicly humiliated that he never led another development of consequence).

Think about a bridge design where an artist and a financier draw up a bridge concept, go through the business case approval, then only bring in the engineer to monitor and control the construction.  Would you want to cross that bridge?  When we come down to it, isn’t that exactly what we have with projects?  Engineering is a professional discipline and has licensing, legal precedent and authority for being engaged in civil projects.  Is that what it would take to get PMs engaged at the start?  Is that what it would take to eliminate Chaos from projects?

© 2014 Chuck Morton.  All Rights Reserved.

Monday, May 5, 2014

Reconstructing Project Management (1 of probably 9)


Does project management cover the management of the project front-end, the definitional, development stages, or is it concerned essentially only with execution delivery?  What should it be responsible for?  How far does it stretch into concept definition at one end and operations at the other?

Morris, Peter.  Reconstructing Project Management Reprised: A Knowledge Perspective.  Project Management Journal, Vol. 44, No. 5, October 2013, p13.

With this post I embark on what I hope will be a series of nine posts, which diverge considerably from how I have historically presented content on this blog.  My focus has been on PM Best Practices and, as a practicing PM, my posts – at least from my perspective – have been intended as practical guides for the functioning PM in the trenches.  For the next couple of months, however, I’m going to wander into the (cue theme from The Twilight Zone) wilderness of PM Existentialism.

Peter Morris authored Reconstructing Project Management (2013) and was invited by PMJ to encapsulate the book for its readers.  If permitted (I’ve asked the publishers of PMJ for permission, which is still pending, to quote from the article for this series), I plan to take nine questions that Morris highlights in the article (Figure 3 Current issues in project management as a discipline, p13) and add my commentary and color, hopefully without getting too lost.

However, I don’t want to give the impression that Morris’ article is these nine questions (which, by the way, are also on page 111 in the book) or, even, that they are the central theme.  In the article’s eighteen pages, Morris condenses, presumably, the topics, points, arguments and themes of two-thirds of his book.  I’m pulling these nine questions, then, completely out of context and I encourage you to read the article (and the book) to understand his thesis.  When I read these nine questions, though, they spoke to me so deeply that I felt compelled to explore them beyond the (here I avoid the use of “mere” or “just”, maybe “unadorned” works) concrete expression that Morris has given us.  Further, I believe there is a tenuous link to my series on Governance.

By tossing these questions, like grenades, on the floor without further expanding on them, Morris challenges us to face the assumptions and core values that define our profession.

Practically a post’s worth of preamble, so let’s get to it…

Enterprise leadership holds their quarterly off-site to review strategy.  They return and the business line VP needs to replace the legacy, proprietary application with a cloud-based SaaS application that is the market leader.  She assigns a director responsibility for accomplishing this, who engages a manager to lead the day-to-day tactical project delivery effort.  The manager, following the company’s methodology, prepares a business case, a charter, a staffing plan and a time and cost schedule.  These are approved by the Director and the project kicks off.

Who is the project manager for this project?

There is so much depth and complexity in Morris’ first question (above).  When I took the PMP certification exam, the model project manager we were told to visualize was the construction PM for whom a sponsor provided money in exchange for a commitment to scope and time.  At that time I worked for a large IT consulting and project management company with aspirations of offering clients responsibility to deliver their projects – high value contracting based on responsibility for deliverables, not time and materials.

Fast forward to the world of today:  that company is limping along as a has-been, ne’er-heard-of-‘em firm and the PM community is bifurcated between reality and wants.  As a profession, we want responsibility for the projects, but in an enterprise reality where, instead, we are just responsible for delivery for someone else.

Executives, managers, and operations leadership make the strategic decisions about what projects to run and have ownership of the operational project decisions (funding, scope, who will be on the team and whether to pull the plug when things go akilter).  They don’t want the mundane tactical responsibilities (and risks) of project delivery, but at the same time there are three market factors that prevent the elevation of professional project leaders into that sphere.  First, those operational leaders, having gotten where they are, are not going to trust someone else with the responsibility (and esteem) for success with their vision.  Second, without projects, their jobs are just, let’s face it, boring.  Projects are the spice to the same daily gruel they otherwise consume (and that consumes them).  They live vicariously through our efforts.

The third condition that reinforces the status quo is that, if other project managers are anything like me, we love delivering projects and don’t want those boring, mundane operational responsibilities.  We are too happy doing what we’re doing to want to trade this for the better world where projects are run by project professionals, but at the cost that we are tied down to quarterly budget cycles, annual personnel reviews (which, btw, should be annual budget cycles and quarterly personnel reviews), product support and maintenance, and enforcing all the petty practices and policies of the very model of a modern major enterprise.

So we take the bones we’re fed, we deliver the project to scope, time and cost (or, in a more mature organization, to process), celebrate the successful delivery, hand it over to them to support, and happily walk away to pre-storm with our next project team.

© 2014 Chuck Morton.  All Rights Reserved.

Wednesday, April 23, 2014

The Tailoring Rule


"Professionalism is knowing how to do it, when to do it, and doing it.”

                                                                                                - Frank Tyger

When people choose to complain about project management, one frequent refrain is the burden and overhead of all that process.  (I believe this is often a red herring, used by detractors who are concerned that project management best practices will expose their delivery weaknesses, but today’s discussion is to address the valid concerns for appropriate levels of process.)

A typical organization does many different types of projects of different sizes, styles and complexity.  For example, an IT department might have projects for:

  • Infrastructure
  • New software development
  • Enhancement and maintenance
  • Product selection, acquisition and installation

Since all projects, regardless of size, style or complexity have many common elements necessary for success, does that mean that the organization only needs one methodology?  Well, yes.  And no.

If the organization has one bloated methodology dictating that all projects must produce all deliverables from identical templates, then those people who complain about too much process have a (partially) legitimate complaint.  It’s legitimate because for most projects there will be too much process, but they are complaining about the wrong thing.

However, there are so many common and essential elements for project success that no organization wants to manage multiple (many?  dozens?) of different, but similar processes.  How to resolve this contradiction?

Both SEI’s CMMI and PMI’s PMBOK® Guide provide for Tailoring.  Tailoring is an important but rarely formally practiced principle.  In fact, in all of my years of consulting across a broad range of companies, I’ve encountered numerous cases where formal practices are ignored or circumvented because they are too onerous or just irrelevant, but in only one case have I worked at an organization that formalized process tailoring.

Even the description in PMBoK does little to suggest that the organization should establish tailoring in the formal processes:  Initiation and Planning includes “guidelines and criteria for tailoring the organization’s set of standard processes and procedures to satisfy the specific needs of the project” (27).  This description makes it sound like tailoring should be done inside the project to customize the organization’s standards rather than that the organization’s standards should specify the tailoring appropriate to different projects.

For example, an IT software development project, an IT software implementation project, an IT infrastructure project and a business process redesign project all have many similarities on how they should be run (they should all have charters, business cases, status meetings, risk logs, change management, etc.), but also significant differences (a new software development project won’t need the RFP activities in the implementation project and the BPR project will need a host of training and documentation activities that will not be needed for a back-office infrastructure project that has no end-user visibility).

Further, for a sufficiently small project, the charter could be fully contained within an email and the change approval process will need to be sufficiently streamlined, since long decision timeframes would jeopardize the delivery of the project.  In contrast, a long, complex, risky project wouldn’t want to make change decisions too informally or too quickly.

The process burden needs to be appropriate to benefit the project – designating those best practices that best assure project success – while addressing project risk without over burdening the project.  A requirements document for a small project might be a few pages, whereas the requirements document for a large, complex project could be a tome, with sections and subsections for business requirements, functional requirements, technical requirements, non-functional requirements, etc.

One size does fit all in project management, as long as that one size addresses the principles of successful project management.  (Is that a tautology?)  Organizations with best practices are clear about what processes are required and how those processes are customized based on type of project, complexity, size, risk.

The mistake often implied by those that complain about excessive process is that the situation would be better if there were no process.  But processes evolved because lack of process (chaos) could not be relied on to consistently deliver successful projects, whereas the use of the processes improved the project success rate.  The solution to excessive process burden (or bad process, for that matter) is not eliminating process.  Rather, the solution is to fix the process through lessons learned and continuous process improvement.

Of course, organizations are even worse at lessons learned and process improvement than they are at projects.  Look for my eventual series on lessons learned to address just this subject.

© 2014 Chuck Morton.  All Rights Reserved.

Friday, October 25, 2013

Project Governance – Maturity Level V

"There is a universality to comedy.”
                                      - Simon Pegg

We have been building to this post for a while now.  This is the final installment of my series on project governance – or, more accurately, governance in the project context.  In the first post I introduced my arbitrary, tongue-in-cheek governance maturity level (gml).  Having covered all of the descriptions for project governance maturity up to this point, it is now time to reveal the ultimate state of governance of interest to project managers.
Historically, the highest level of governance is some variation on the theme of continuous improvement or optimizing, but I announced in my previous post that that was not the case for this maturity model.  And that post described the penultimate maturity level as alignment with organizational strategy, so what remains for the highest level of project governance maturity?

For strategic projects, there are really only three reasons that justify the project:  it increases revenue;  it reduces cost;  it is a regulatory requirement.  (Do you know of any other reasons that legitimately justify a strategic project?)  For most enterprises, what department has the highest stature?  Marketing?  HR?  Procurement?  FINANCE (hint hint)?  Of course it’s finance.  And it’s time finance started seeing projects as generating revenue or reducing expenses.
In May, Angelo Baratta presented a webinar for PMI’s Information Systems Community of Practice titled “The Value Triple Constraint: Project Value Left Behind” (PMI and ISCoP membership required).  In it, Baratta reminded us that projects have an economic benefit to the organization.  So often as project managers, we are focused on cost (along with time and scope) and leave benefit and value to the cost-benefit analysis or the charter – and to bean counters or stakeholders with “higher pay grade.”  But because there is this positive financial component, delays (among other choices) have a financial impact to the organization.

The highest level of project governance maturity, then, is when projects are recognized as enterprise assets.  Just like raw materials and capital investments, we (the PM community) should be lobbying to have our projects recognized as corporate assets.  This would immediately transition us to the big leagues.  Our babies would be elevated in stature within the corporate and political pecking order.  Project choices (delay, increase scope, cut scope, etc.) would have clear financial impact to the organization.  Getting resources, as Baratta noted in his presentation, would be straightforward to justify when the alternatives can be quantified.
Of course, these benefits don’t come without perils, but such is the consequence of maturity.  We will no longer be able to operate informally.  We will operate in the spotlight.  We will have to learn to speak “executive” (cut your vocabulary in half!).  Risk management will impact the corporate risk profile.  Governance in the project context will be integrated into the organization’s financial governance (think Sarbox).

One of the objectives of PMI is to have “Project Management” recognized as a discipline (or profession) distinct from “Management.”  A step in this direction is to elevate the governance maturity and to transition project delivery from a technical discipline to a financial discipline with direct consequence for the enterprise bottom line. 
From gml-I Chaos, gml-II Solution, gml-III Consultancy, and gml-IV Alignment, we have climbed the maturity staircase.  Getting to gml-V Capitalized is governance your CFO would recognize – the next stage in PMI maturity.

Has this journey been worth it?  What changes would you make to gml?  Or how would you define a project governance maturity model?
© 2013 Chuck Morton.  All Rights Reserved.

Saturday, October 19, 2013

Project Governance – Maturity Level IV

The alignment of the project with stakeholders’ needs or objectives. (p30)

Project Governance: The alignment of project objectives with the strategy of the larger organization by the project sponsor and project team.  A project’s governance is defined by and is required to fit within the larger context of the program or organization sponsoring it, but is separate from organizational governance.  (p553)
                                                                                                - PMBoK v5

This is the fourth and penultimate installment of my series on project governance – or, more accurately, governance in the project context.  In the first post I introduced my arbitrary, tongue-in-cheek governance maturity level (gml) and expanded on the subject in the second and third posts.  With this post, we advance to describing gml-IV, moving beyond the strict focus on project governance.
Project governance is needed – that is, there need to be controls in place to assure project delivery according to the organization’s defined processes.  But project governance alone is not sufficient for most organizations.  Successful projects (completing projects successfully) assumes that the right and proper projects are being done.   In fact, The Guide to the Project Management Body of Knowledge (PMBoK) has almost no references to project governance.  All references to “governance” are either in the introductory first two chapters or are in an appendix (such as the definition, above).  As these representative quotes indicate, for PMI project governance is more about delivering the right project than about delivering the project right.  (In contrast, for Microsoft Solutions Framework, governance is strictly about delivering the solution.)

The interesting thing is, there is another accepted term for doing the right project:  project portfolio management.  But project portfolio management, like any other process or methodology, needs to be paired with a governance structure.  There need to be checks and balances, oversight, and independence.  These governance processes need to integrated with organizational governance, most appropriately around strategic planning and success.
With my next post, the final post in this series, I will introduce gml-V.  Everyone, of course, already knows that gml-V, like all good maturity models, will be about continuous improvement, what SEI CMMI calls Optimizing.  Surprise:  that isn’t what gml-V is.  So stick around, read the next post and be surprised.

You’ve read what I’ve posted on governance so far, so what would be your five governance maturity levels?  Specifically, what would you have for the highest level of project governance maturity?
© 2013 Chuck Morton.  All Rights Reserved.

Wednesday, October 9, 2013

Project Governance – Maturity Level III

Project governance is an oversight function that is aligned with the organization’s governance model and that encompasses the project life cycle.  Project governance framework provides the project manager and team with structure, processes, decision-making models and tools for managing the project, while supporting and controlling the project for successful delivery.

                                                                                                - PMBoK v5 (p34)
This is the third post in my series on governance in the project context.  In the first post I introduced my arbitrary, tongue-in-cheek governance maturity level (gml) and in the second post described gml-II Solution, the first level of maturity of project governance.  With this post, we advance to describing gml-III.

Remember from the previous post that minimal project governance is focused on the project solution.  Advanced project governance, in contrast, is focused on project delivery.  Rather than just being concentrated on Executing Process Group (PMBoK v5 section 3.5) activities, gml-III governance covers the entire gamut of process groups:  Initiating, Planning, Monitoring and Control, and Closing.

At gml-II, governance activities were directed at the product deliverables.  At gml-III, in contrast, expect the governance team to examine the project charter, statement of work, status reports, meeting minutes, and all deliverables in the organization’s methodology, all the way through to the project retrospective and closing.  Not only will they be looking to see that the work product was produced, but that the proper template was used, the content conforms to standards, it was distributed properly (both audience and time), and that approval authorities are correct.
While governance processes may be similar to those at gml-II, the tools used at this level are ratcheted up.  Periodic audits with formal auditing checklists, scoring models (i.e., a project that is not conforming to process is higher risk than one that does), and public, structured project reviews are all normal practices.  These audits and reviews are distinctive in that performance is not determined by time, cost or scope;  performance is exclusively measured by conformance to process and proper use of tools by the right people.

At this level, there are also differences from the previous level with the governance team.  All governance is a form of “Check and Balance” to assure credibility.  At gml-II, project governance is within the project delivery methodology, for example, stage gates.  As such, it is contained within the department or division;  it might even be within the PMO.  At gml-III, in contrast, the concern for credibility goes much higher in the organization, thus governance is completely separate from the project delivery organization.  At a pharmaceutical company, for example, governance may report up through the legal department;  at a financial institution, depending on what department the project team is in, governance may report to legal or to the CFO;  in a large (completely projectized) consulting firm that I worked for for many years, the governance team reported directly to the COO.  That is, the project delivery organization existed, with branches, branch managers, PMs, Delivery managers, divisions, VPs, etc.  But governance was completely independent of the project delivery organization.  The project auditors that worked at the branch level did not report to the branch managers, but reported up through their own hierarchy that reached directly to the company president.  This demonstrates that gml-III is the appropriate governance level for the consultancy PM.
My final comments on gml-III are that, because the governance elements are formal and process-ized, the environment is positioned for continuing process improvement.  The project audits will encourage post-project reviews and documented Lessons Learned.  These will, in turn, be fed back as inputs into the project audits, resulting in improvements to the checklists, tools, templates and training.  This virtuous cycle represents the capstone of gml-III maturity.

In my first post in this series, I mentioned that we would explore governance in the project context.  So far, we’ve been exclusively discussing project governance, but with the next post, on gml-IV Alignment, we will step outside the project to see what penultimate governance looks like in a project organization.
When governance is discussed, someone usually bemoans the inefficiency, the overhead, the burden.  Does your organization have too much, too little or just the right amount of governance?

© 2013 Chuck Morton.  All Rights Reserved.

Monday, October 7, 2013

Project Governance – Maturity Level II

"I think the next best thing to solving a problem is finding some humor in it”

                                                                                                - Frank A. Clark
In my previous post, the first post in this series on governance in the project context, I introduced my arbitrary, tongue-in-cheek governance maturity level (gml) and described gml-I Chaos.  With this post, we advance to describing gml-II, the first maturity level where governance is contributing to project success.
Effective governance is external to the project (and therefore to the project team).  I’ll dwell on this more in a later post in this series, but this means that project governance cannot be performed by the project manager;  governance is someone outside the project looking at what the project manager and the project team have done.  Other requirements for the organization to be at gml-II are a project methodology, project standards, and deliverable templates, since, for governance there must be something to govern to. 

At the lowest level of mature project governance, the attention is on the project solution, the product or service , such as in the Product & Service Delivery (P&SD) organization.  Governance at this level is focused on the Executing Process Group (PMBoK v5 section 3.5) activities and the product deliverables.  Examples of project governance activities at this level include architectural reviews and stage gate reviews.
Another factor I check is how the project managers are measured and incented.  This is a topic I touched briefly a while back (How Should a Project Manager be Measured?), so I won’t dwell on it here.  Suffice it to say, though, that if the organization has a methodology and standards and the PM is not measured (and incented) based on those standards (rather than the PM Triple Constraints), then the organization is most likely still at gml-I Chaos.  After all, the organization is sending a mixed signal on whether they want the PM to follow the standards or to abandon them to deliver the product or service solution any way they want.

Governance models that describe governance maturity level II are Microsoft Solutions Framework (MSF) and the SEI Capability Maturity Model – Integrated (CMMI), which are both solution-focused methodologies.
In my next post, we’ll move slightly up the food chain to gml-III Consultancy, which will discuss a more advanced implementation of project governance.

Does your organization have effective project governance?  How does it stack up so far based on this description?  Do you think I’ve fairly described minimal project governance?
© 2013 Chuck Morton.  All Rights Reserved.