“The first step in the
risk management process is to acknowledge the reality of risk. Denial is a common tactic that substitutes
deliberate ignorance for thoughtful planning.”
-
Charles Tremper
With this post, we conclude the series on developing the well-formed
schedule. We have taken the WBS,
which defines the project scope, added the task dependencies, estimated the
effort for each task, assigned resources to each task, and resource-leveled the
task assignments. The final step to
complete the well-formed schedule is to add risk buffers so that the schedule
has the intended probability of success.
A schedule without risk buffers has virtually no probability
of success. Since you probably want to
present a schedule with some probability of success, it obviously follows that
you must add some risk buffers. So now
you probably want me to tell you how many and where.
I’ll briefly identify two common practices for identifying
risk buffers. The first is built from
the standard risk management process.
The PMI PMBoK risk management process includes the step “Quantify
risks.” You’ve probably wondered what
this means. For risks that should be
mitigated, determine the probability of occurrence (a percentage) and the time
and cost that must be added to the project if the risk event occurs. Let’s say for a specific risk you determine
there’s a 25% probability that it will occur and that if it occurs it will add
12 weeks (I’m just going to deal with time in this example, but you can
extrapolate for costs) to the schedule.
The 25% probability times the 12 weeks is 3 weeks, meaning that you
should add a risk buffer of three weeks to your schedule.
Depending on a variety of factors, you can either add all
three weeks to the end of the schedule or spread it in appropriate points over
the life of the project.
You repeat this for all significant project risks.
A very common alternative to this approach is to use the Critical Chain approach developed
and promoted by Elihayu
M. Goldratt. It uses a formulaic
approach to determine the appropriate amount and placement of the risk buffers.
This overview is obviously too high a level for practical
application. But with this post I’ve
finally presented enough of the PM foundation so that I can introduce some of
the more interesting and complex concepts.
I’ll do this starting with a couple of posts on advanced quantification
of the schedules, then maybe transition to more fully explaining the
development of risk buffers.
It’s taken me two years of posts to get to “the fun stuff.” What area of project management best practice
would you like me to tackle?
No comments:
Post a Comment